PROJECT PROFILE |
|
Project | Coca Cola Building Demo |
Location | Northeast |
Dates | 2021 |
Client | N/A |
Value | <$200,000 |
PROJECT REQUIREMENTS
- Wrecking
- Abatement
OVERVIEW
EBD was contracted to provide temporary fencing, terminate utilities to the building, and remove asbestos floor tile and windows before demolition. The building was then demolished as controlled demolition with asbestos in place. The building foundations were removed, and the site was regraded with onsite materials to fill voids.